New Water Lines West Side
Description
New Water Lines to west side map_thumb.jpg
This project will consist of obtaining water line easements, design, and construction of approximately 27,550 linear feet of 24-inch water transmission line and 6,900 LF of 16-inch waterline. The 24-inch line will run from the Calder Road pump station south to the future Grand Parkway and head west to the future Bay Area Blvd. extension and continue north along Bay Area Blvd. north to the American Canal. The 16-inch waterline will follow the future Bay Area Blvd. extension from south of the future Grand Parkway easement to FM517.

2013 CRF study reflects 9,050 LF of the 24-inch waterline project costs are eligible for Water CRF funding.

Why does League City need it?
This line is necessary in order for the City to be able to provide water supply for future capacity demands and to provide a looped system with the City's existing west side infrastructure to maintain adequate system capacity, pressure, and fire protection to the existing west side development.

Need more information?
Looking for financial information or more? You can view the most recent quarterly and monthly status reports with more detail by clicking on the following: Status Reports Quarterly reports will give you where we are at in the budget for the project and monthly reports will give you the latest status updates on active project.