60” Water Line to replace 42” line on SH3
Screen Shot 2013-08-29 at 10.54.21 AM.pngDescription
This COH project is for the design and construction of 47,500LF of 60" Water Line along Old Galveston Rd to replace the current 42" line from the Southeast Water Purification Plant (SEWPP) on SH3. 2013 CRF Study reflects 19.5% of project costs are eligible for Water CRF funding.

Why It's Needed
This project is necessary due to the age of the current 42" line, to increase the capacity of the line with the anticipated additional supply, and TxDOT plans to widen SH3 to meet hurricane evacuation route criteria.

Need More:
Looking for financial information or more? You can view the most recent quarterly and monthly status reports with more detail by clicking on the following: Status Reports Quarterly reports will give you where we are at in the budget for the project and monthly reports will give you the latest status updates on active project.

Have an opinion, question, or concern? We want to hear it! Fill out this form and someone from city staff will contact you asap!