Jag Hollow Extension
Screen Shot 2013-08-29 at 1.52.01 PM.pngDescription

Extension of Jag Hollow from I45 feeder to Walker Street.


  • FY2012 project: Design of Jag Hollow Extension, Ph 1 & 2 (I45 feeder to Walker St - Victory Lakes area on East side of I45) 
  • FY2013-2014 project:Phase 1 Construction of Jag Hollow Extension (I45 feeder to Town Center Blvd) 
  • FY2017 project – SCHEDULE DEPENDENT ON DEVELOPMENT: Phase 2 Construction of Jag Hollow Extension (Town Center Blvd to Walker St)  
  • Budget: $300K ROW + $652K Construction = $952K

Why It's Needed
To make this site marketable for Economic Development.

Need More:
Looking for financial information or more? You can view the most recent quarterly and monthly status reports with more detail by clicking on the following: Status Reports Quarterly reports will give you where we are at in the budget for the project and monthly reports will give you the latest status updates on active project.