Traffic Development CIP Projects

This program is to upgrade components on existing signals, improve timing, and construct intersection improvements to improve mobility throughout the city. The Fiber Network Traffic System West Side project has $334K in FY 2015 to install fiber from Texas Ave to Bay Area Blvd.  This will give the traffic signals the ability to communicate effectively and provide improved signal timing and progression along the major corridors.  There is also $482K in grant funds to install battery backup and surge protection systems at traffic signals and install LED signal heads and luminaires and pan/tilt/zoom cameras along with fiber/wireless communication.  The final design of the North Landing Boulevard extension and beginning design on the Ervin/Hobbs connector are included in FY2015.  Also included in the five-year plan is funding for new traffic signals in key locations that currently have four-way stops, construction of the North Landing Extension and Ervin/Hobbs connector, and a traffic study along the FM270 and SH96 corridors.


View larger map

This product is for informational purposes and may not have been prepared for or be suitable for legal, engineering or surveying purposes. It does not represent an on-the-ground survey and represents only the approximate relative location of property boundaries and/or any other feature represented on this map

Projects In Progress At A Glance: (as of August 2016)

SH96 Corridor Traffic Study:  FY 2016: To study the FM270 corridor from Kroger to FM646 and the SH96 corridor from I45 to SH146 for targeted improvements in traffic flow and areas prone to congestion.  The study will explore the traffic flow at intersections, possibility of adding right turn lanes, and over all travel times for potential improvements with estimated construction cost.  Received 100% plans; kick off lane additions on 7/27/16.

FM 270 at Austin Traffic Signal Design:  Design services to prepare bid documents, TXDOT permit for mast arm traffic signal.  PSA executed February 1, 2016; design completion scheduled early July 2016.  Anticipated bid September 2016.

SH 96 at SS Blvd. Intersection Improvements:  Intersection improvements to SH 96 at South Shore Boulevard.  PSA executed March 7, 2016; design completion anticipated mid-September 2016.

Fiber Network Traffic System to West Side: Bids opened and rejected June 14, 2016.  New prebid was July 13th with bids closing July 26th.

Ervin/Hobbs Connector Design Contract awarded by Council October 13, 2015.  Design completion scheduled for December 2016.  Anticipated bid FY 2018.

Traffic System Improvements:  Design traffic signal at the intersection of Calder and FM517 on hold pending funding; Design of signal has been delayed pending development of funding partner. Signal was submitted for state grant funding by June 2015; project was not selected for funding by TXDOT. Requests sent to City of Dickinson and Galveston County in December with no response to date.

Need More:
Looking for financial information or more? You can view the most recent quarterly and monthly status reports with more detail by clicking on the following: Status Reports Quarterly reports will give you where we are at in the budget for the project and monthly reports will give you the latest status updates on active project.