Water Line Development CIP Projects

Water system improvements represent the single largest program category with $105.6 million in projects to be funded during the FY 2015-2019 period.  These projects focus on improvements to the distribution and renewal of the existing water system and address obtaining new supply and its distribution.  New bond financing backed by utility revenues over five years is required for $84.1 million of this total.  Key projects in FY 2015, with a total of $23.5 million in funding, include construction of 36-inch waterline from SH3 booster station to South Shore Harbour booster station, construction of segments 3-5 of the southeast service area trunk lines, annual waterline upgrades and replacements, and construction of the new east side elevated tank and well.

Also included in the proposed CIP is League City’s proportional share (estimated at $43.6 million) of the expected construction by the City of Houston of a 60-inch upsized replacement for the 42-inch water line down State Highway 3.  This line provides 68 percent of League City’s current surface water supply.  



View larger map

This product is for informational purposes and may not have been prepared for or be suitable for legal, engineering or surveying purposes. It does not represent an on-the-ground survey and represents only the approximate relative location of property boundaries and/or any other feature represented on this map

Projects In Progress At A Glance: (as of August 2016)


New East Side Elevated Tank #1: Construction awarded July 14, 2015; anticipated substantial completion January 2017

South Shore Harbour Pump Station: Construction awarded April 8, 2014; project beneficial use December 2015. Demo completed February 2016; site work and cleanup complete June 2016.  Negotiating final change request.

Southeast Service Area Trunks: Design contract awarded for section 3-5 May 14, 2013; preliminary discussions with land owners regarding right-of-way needs September 2014; staff reviewing 60% plans May 2014; right-of-way acquisition underway; anticipated construction of sections 3-5 in FY 2017.

36" Water Line to SH3 to SSH Booster Station:  Design:  identified route, coordination with all regulatory agencies, began project planning, geotechnical, pipeline coordination, met with Parks Board, and identified easements required; property appraisals complete; plans in review by CenterPoint Energy.  Anticipated Construction bid August 2016 with award September 2016.

Calder Rd Pump Station:  Staff is satisfied with condition of land;  staff is coordinating with sewer line; Council awarded construction March 25, 2014; notice to proceed August 4, 2014; project beneficial use in March 2016.  CO #1 in process; will extend contract time to September 2016.

Water System Improvements - Dickinson Water Well:  Bid in October 2015; awarded in November 2015.  Construction NTP issued February 2016 with 180 day contract.  Contractor completed well drilling July 2016.  GLO amendment in process to add engineering and funding for construction of a surface water blending line to pretreat well water.

Water Line Upgrades & Replacement: Council approved design of Old Town North Area (north of FM518, east of SH3, west of FM270, and south of Clear Creek) January 14, 2014; design complete.  Construction began February 2016 with 300 day contract; substantial completion anticipated December 2016.

New Water Lines to the West Side:  FY2016 Project- 24-Inch line to run from the Calder Rd. Pump Station south to the future Grand Parkway to head west to the Future Bay Area Blvd. extension and continue north along Bay Area Blvd. to the American Canal.  The 16-inch water line will follow the future Bay Area Blvd. extension from south of the future Grand Parkway easement to FM 517.  Subject to possible developer agreement, design anticipated  FY2018.

SEWPP Treatment Improvements: This project is based on anticipated treatment improvements at the SEWPP which co-participants (GCWA) will owe a portion of.  Programmed for FY2016 based on estimates from City of Houston for when actual cost are determined. 

60" Water Line Replace 42" Line on SH3: Preliminary design has begun, land acquisition in FY2015-16, and construction FY2019.

24-Inch Water Line Stabilization:  FY 2016:This project is to stabilize the 24-inch waterline along League City Pkwy (SH96) that runs along the bank of Gay's Pond. Phase 2 survey completed February 2016; recommendation expected October2016

DSWWTP Reclaimed Water Pump System: Design consultant is evaluating using Alabama Tank to meet TCEQ regulations for a pressurized delivery system and determine peak system capacity; developing rate schedule with update to feasibility study and formalize project delivery schedule.

Need More:
Looking for financial information or more? You can view the most recent quarterly and monthly status reports with more detail by clicking on the following: Status Reports Quarterly reports will give you where we are at in the budget for the project and monthly reports will give you the latest status updates on active project.