Go To Search
City Council and Boards and CommissionsDepartments - City ConnectionsResidents - Resources and InformationPublic Works Department Services
Click to Home

Wastewater Development CIP Projects

Wastewater’s total program for the five year CIP period totals nearly $31.16 million for lines and lift station improvements and expansion in the re-use system.  FY 2015 projects (funded at $11.28 million total) include construction of Hobbs Rd Lift Station/Force Main/Gravity Sewer; upgraded force main from Bay Colony lift station to Ervin Street; improvements to the re-use utility system;, construction of a new 30-inch gravity sewer line on Calder Road;, and Countryside Wastewater Treatment Plant demolition. This category also includes Sanitary Sewer Rehab,  an ongoing project with $7.5 million allocated in FY 2015-2019 for ongoing as-needed improvements to the City’s sanitary sewer system.  

View larger map

This product is for informational purposes and may not have been prepared for or be suitable for legal, engineering or surveying purposes. It does not represent an on-the-ground survey and represents only the approximate relative location of property boundaries and/or any other feature represented on this map

Projects In Progress At A Glance: (as of September 2016)

Re-use Improvements, Ph 1: Design consultant is evaluating using Alabama Tank to meet TCEQ regulations for a pressurized delivery system and determine peak system capacity; developing rate schedule with update to feasibility study and formalize project delivery schedule.  This Project is on Hold.

Annual Sanitary Sewer Rehab:  FY2014 project locations along SH3, Patton Subdivision, and a majority of Bay Ridge subdivision: Construction project substantially complete.  FY2015 project sanitary trunk systems include: 1) a 24-inch ductile iron sanitary sewer trunk main along FM 2094, from SS Blvd. to the East Main LS, and; 2) a 42-inch thru 48-inch ductile iron sanitary sewer trunk main along Coryell St., from FM 270 to the Dallas Salmon WWTP. Construction contract awarded June 28, 2016.  FY 2016 Sanitary Sewer Rehab design completed  August 2016 for the Landing Subdivision.  Bids received September 27, 2016. Award of construction contract scheduled for October 25, 2016 council agenda.

Westside 54" & 42" Gravity Sewer Interceptors, PH 1:  FY2016- Extending south from the SWWRF following along the future Grand Parkway alignment, 750 LF of 54" gravity sewer from the SWWRF to the Grand Parkway alignment.  Then 42" gravity sewer following along the future Grand Parkway alignment east 10,850 LF.  Schedule to be determined.

Bay Area Blvd. 12" Sewer Improvements FM/LS:  FY2016- Design and Construction of 4,550 LF of 12-Inch sewer, a lift station, and 600 LF of 8-Inch force main along the future Bay Area Blvd extension.  Schedule to be determined.

MUD 14-15 Lift Station Improvements:  Lift Station re-evaluation by Jones & Carter, Inc. approved for design in July 2016.  Design anticipated to be complete November 2016.

Re-use Utility System: Design on hold until Re-use Improvements, Ph 1 (WW1101) project delay is resolved; consultant is evaluating using Alabama Tank to meet TCEQ regulations for a pressurized delivery system.  This Project is on Hold.

FM Upgrade Bay Colony LS to Ervin:Design 100% complete; survey complete; anticipate construction bid FY2016 subject to 15 easement acquisitions and coordination with the Calder sewer line and a developer.  Redesign to shorten Force Main pending approval of design contract addendum with Jones & Carter, Inc.  Anticipate Force Main bid Fall 2016.

Dallas Salmon Effluent Discharge Improvements:
  FY2016- Structural modifications to existing effluent discharge structure and the installation of approximately 1,500 ft. of 84" concrete conduit from the Dallas Salmon WWTP discharge structure, following the perimeter of the fire training facility, continuing northwest along Kansas St. to the banks of Clear Creek.  Awarded Design contract January 2016; final design completion expected June 2017.

Hobbs LS/FM/GS: Design 100% complete; Property acquisition complete June 2014; construction awarded February 24, 2015 with completion anticipated August 2016 - utility conflicts resolved.

30" Gravity Line - Calder:  Phase I complete.  Phase 2: Substantially complete November 2016.

MUD #6 Lift Station Rehab: Substantially complete February 2016.

Annual Lift Station Improvements:  FY2015 project:  (1) South Shore Harbour #3 LS Improvements:  Under Construction with anticipated completion by January 2017.

Big League Dreams & Brookport Dr. 15" Sanitary Sewer Improvements: Substantially complete.

Need More:
Looking for financial information or more? You can view the most recent quarterly and monthly status reports with more detail by clicking on the following: Status Reports Quarterly reports will give you where we are at in the budget for the project and monthly reports will give you the latest status updates on active project.

Have an opinion, question, or concern? We want to hear it! Fill out this form and someone from city staff will contact you asap!